How long does a bathroom renovation take?

A complete bathroom renovation takes about 4 weeks on site. An ensuite takes 2–3 weeks, and a bathroom where the plumbing moves takes 5–6 weeks. Kitchens take 5–7 weeks because the cabinetry has to be manufactured first.

MelReno’s own prices, all including GST. Prices checked October 2026.

JobTime on sitePrice from (GST in)
Ensuite / small bathroom2–3 weeks$14,999
Complete bathroomAbout 4 weeks$19,999
Bathroom with layout changes5–6 weeks$29,999
Kitchen facelift1–2 weeks$10,999
Complete kitchen5–7 weeks incl. joinery$24,999
Custom kitchen8–10 weeks$34,999

What happens in those four weeks

  • Strip-out. Tiles, fixtures and wall linings out, rubbish into the skip. This is where hidden damage shows up in older homes — if it does, you get a written price before anything else happens.
  • Rough-in. Plumbing and electrical run to the fixture positions.
  • Waterproofing. Applied to AS 3740 and left to cure before any tile goes on.
  • Tiling. Floor and walls.
  • Fit-off and handover. Vanity, toilet, screen and tapware go in; you get the waterproofing certificate and a walk-through.

What makes it take longer

  • Moving plumbing to new walls (adds 1–2 weeks)
  • Damage found behind the walls or under the floor
  • Changing a fixture or tile choice after work has started

You get the start and finish dates in writing, and we start when we say we will. We would rather quote a date we can hit than a short one we can’t.

Book a free site inspection Find your suburb

Questions people ask

How long does a complete bathroom renovation take?

About 4 weeks on site with MelReno for a complete bathroom with fixtures staying in place.

How long does an ensuite renovation take?

2–3 weeks on site for a standard ensuite or small bathroom up to about 4 m².

How long if we move the shower or toilet?

5–6 weeks. Moving plumbing to new positions adds roughly one to two weeks to a complete bathroom.

How long does a kitchen renovation take?

A complete kitchen takes 5–7 weeks including joinery, because cabinetry takes 6–8 weeks to manufacture after the layout is signed off. A facelift takes 1–2 weeks.

Will I get the dates in writing?

Yes. Start and finish dates are written into the quote, and we start when we say we will.

More on prices

Free, no obligation

Thinking about the existing house?

Free site inspection, one itemised written price, and an honest answer about what your budget will and won't stretch to. Complete bathrooms from $19,999 all inclusive.

Please enter your name
Please enter a valid phone number
Please enter a valid email
Please enter your suburb
Please choose a project type

We use these details only to contact you about this enquiry. The form is delivered by Formspree, which stores submissions in the United States — see our privacy policy, or email us directly if you would rather not use it.

Or call 0422 704 537 — Mon–Sat, 7am–6pm.

Thanks — we've got it.

We'll call you back to arrange a time, usually the same day.